Project Description

Do You Have A Project We Can Help With?

CONTACT US

National Grid – Bolney Sub Station

As part of a regional substation upgrade IPS Power were employed by Grosvenor Power to install new 415v power supplies.

This required the installation of 4 x 240sq mm cables into existing cable troughs to termination switch-gear. The cable troughs contained existing  compressed air pipes operating at high pressure which required special protective  measures during the cable installation.

Additionally to avoid the hazard of induced voltage into wire cable pulling bonds Kevlar rope was used to mitigate the problem and maintain safe working conditions.

Project Details
DATE

February 2019

CLIENT

Grosvenor Power for GE